How much work is left in the fee?

Start with the signed fee. Subtract delivery costs already incurred and what you expect it will take to finish. Update that estimate whenever the scope changes.

Discuss a project forecast

Illustrative example

$6,000

projected contribution

Project completion forecast
Signed project fee$24,000
Delivery costs to date−$10,000
Estimated cost to finish−$8,000
Projected contribution$6,000

Fictional figures, not client results.

What the numbers tell you

If the remaining work costs an extra $3,000, projected contribution drops to $3,000 before overhead. The invoice total hasn’t changed, but the project outlook has.

What to bring

  • Signed scope and change orders
  • Staff time, contractor bills and project costs
  • The project lead’s estimate to finish

No financial records are needed for an initial inquiry.

How Dormie can help

Controller + FP&A may fit if you want to review forecast scenarios instead of waiting until the job closes. The forecast depends on your team’s delivery assumptions.

Compare service plans and pricing

Common questions

What is an estimate to complete?

It’s the expected cost of the work you still owe on a project. Combine it with costs to date and compare the total with the fee to estimate project contribution.

Is a deposit the same as project margin?

No. A deposit tells you when cash arrived. Margin depends on the fee and the costs of delivering the work. Track those questions separately.

Let’s talk

Let’s talk about
your books.

Tell me a little about your business. I’ll follow up to discuss what you need, whether Dormie is a fit, and the scope and pricing.

Let’s talk