What is an estimate to complete?
It’s the expected cost of the work you still owe on a project. Combine it with costs to date and compare the total with the fee to estimate project contribution.
Who we serve
Start with the signed fee. Subtract delivery costs already incurred and what you expect it will take to finish. Update that estimate whenever the scope changes.
Discuss a project forecastIllustrative example
$6,000
projected contribution
| Signed project fee | $24,000 |
|---|---|
| Delivery costs to date | −$10,000 |
| Estimated cost to finish | −$8,000 |
| Projected contribution | $6,000 |
Fictional figures, not client results.
If the remaining work costs an extra $3,000, projected contribution drops to $3,000 before overhead. The invoice total hasn’t changed, but the project outlook has.
No financial records are needed for an initial inquiry.
Controller + FP&A may fit if you want to review forecast scenarios instead of waiting until the job closes. The forecast depends on your team’s delivery assumptions.
Compare service plans and pricingIt’s the expected cost of the work you still owe on a project. Combine it with costs to date and compare the total with the fee to estimate project contribution.
No. A deposit tells you when cash arrived. Margin depends on the fee and the costs of delivering the work. Track those questions separately.